executed one of the largest Solar Rural Electrification project in the world, at Mundanmudi, Idukki district, in the highlands of Kerala, India, where 400 houses
of a single village was electrified using Solar power. The project also set a
new industry standard in the country with TeamSustain offering a five year
maintenance contract with locally trained resident technicians. The trouble free
maintenance contract ended in October 2002.
|
Name of the site |
Mundanmudy, Idukki, Kerala, India |
|
Type of project |
Solar Rural Electrification |
|
Area of project |
5 square Kilometers |
|
Technical details |
Solar power pack for 400 houses powering 2 CFLs of 7 or 9 watts each and a radio or television point |
|
Cost of project |
US$ 0.16 million |
|
Government support |
80% of the project funded by the Japanese Government |
|
Collaboration |
Local NGO CASP - Cochin |
|
Duration of the work |
02 months |
|
Year of installation |
October1997 |
|
Name of site |
Sythite Industrial Chemicals Limited, Karamadia, Coimbatore ,Tamil Nadu, India |
|
Type of project |
Solar assisted Air Drying System |
|
Size of the project |
Collector surface area - 1350 square meters |
|
Technical details |
Solar panel from solar wall USA with an area of 1350 square meters of which 300 square meters is glazed area with toughened glass |
|
Cost of project |
US$ 0.11 million |
|
Government support |
None |
|
Collaboration |
Conserwall Inc., Canada and USA |
|
Duration of work |
03 months |
|
Year of installation |
Year 1998 |
|
Post installation service |
One year warranty |
|
New savings achieved |
Replaces between 750-900 liters of diesel per day.
Average savings |
|
Name of site |
Periyar Mannimmai College of Technology for Women, Periyar Nagar, Vallam, Thanjavor, Tamil Nadu , India |
|
Type of project |
Biomass gasification power generation. |
|
Technical details |
100 KW gasification system using briquette coir path and wood chips as feeder material. The system consists of 100 Kg/hr. reactor, scrubber, cooler, condenser centrifugal tar removing attachment, chilling plant and 180 KVA Greaves diesel generator set |
|
Cost of project |
US$ 0.1 million |
|
Government support |
None |
|
Collaboration |
Associated Engineering Works |
|
Duration of work |
04 months |
|
Year of Installation |
Year 2002 |
|
Saving and pay back details |
Rs. 01.25/unit (0.03 US cents) 04 years payback period |
|
Post installation service |
01 year service warranty |
|
Name of Site |
Sythite Industrial Chemicals Limited, Karamadia, Coimbatore, Tamil Nadu, India |
|
Type of project |
500 KW Thermal Gasifier Project |
|
Area required |
1500 square feet |
|
Technical details |
500 KW fully automatic gasifier with coconut shell as feed material. The system consists of 500 Kg/hr. reactor, automatic ash removing system, biomass conveyors, cleaning system |
|
Cost of project |
US$ 0.22 million |
|
Government support if any |
Subsidy from Tamil Nadu Energy Development Board |
|
Collaboration |
The Indian Institute of Science (IISC), Bangalore, India |
|
Duration of work |
08 months |
|
Year of installation |
May, 2000 |
|
Saving and pay back period |
150 litres diesel/hr, 3000 litres diesel/year. Less than 01.5 year on investment |
|
Post installation service |
02 service warranty |
Contact us by phone at: 1-888-233-9266 Ext 89 in the USA or +91-484-3298806/3298807/3295204 in Asia